Brickie was back on site today to create the doorway between the master bedroom and walk-in closet above the garage.
Photo 1
Photo 2
Photo 3
Creating the opening using an angle grinder produced unbelievable amount of dust.
Photo 4
Photo 5
This will be the doorway from the master bedroom into the walk-in closet/dresser and en-suite above the garage. Due to the height constraints, we will require some steps down from the bedroom.
Grab lorry arrived to remove more muck Photo 1 Photo 2 The damp proofing was also applied in the hallway. Although it was suggested to take the damp proofing up to 1m, it would have required removing all the skirting and dado-rails. We decided against it as the existing damp course was doing its job so we just applied it below the finished floor level as that wont be accessible. Photo 3 Photo 4 Photo 5 Photo 6 Photo 7 Photo 8 Photo 9 Photos 5 to 9 show the foundation masonry being constructed. This will all be below ground level and won't be seen. Previous Next
Brickwork has been progressing on the garage. The difficulty has been finding and cleaning the best of the salvaged bricks to reuse. Photo 1 Photo 2 Photo 3 Photo 4 Photo 5 Photo 6 Photo 7 Previous Next
The demolition of the conservatory continues... Managed to salvage around 200 of these bricks which I'm thinking could be used for flower beds or an outdoor BBQ in the future. Previous Next
Comments
Post a Comment