Day 15 - Foundation Masonry

Grab lorry arrived to remove more muck
Photo 1

Photo 2

The damp proofing was also applied in the hallway. Although it was suggested to take the damp proofing up to 1m, it would have required removing all the skirting and dado-rails. We decided against it as the existing damp course was doing its job so we just applied it below the finished floor level as that wont be accessible.
Photo 3

Photo 4
Photo 5

Photo 6

Photo 7

Photo 8

Photo 9
Photos 5 to 9 show the foundation masonry being constructed. This will all be below ground level and won't be seen.