Day 69 - Roofing

The roofers were back today to finish off installing the rafters. Our bricklayer had also recovered and was on site to complete the wall.

Photo 1
 Not very clear but Photo 1 shows some blocks added to the wall for the wall plate to sit on.

Photo 2

Photo 3
 Photo 3 showing the brackets to the trusses and straps from the wall plate to the blockwork.

Photo 4
Gable wall being built.

Photo 5

Photo 6
We removed the roof window in the centre, so that there remains only the 2 as originally planned.

Our bricklayer finished the blockwork for the gable wall and we're hoping the remaining blockwork for the kitchen will be completed tomorrow - weather dependent.




Comments

Popular posts from this blog

Windows and Doors

Day 59 - Brickwork

Day 2 - Site Clearance