Day 109 - Brickwork

Due to the slope of the garage roof, one of the bathroom windows needs to blocked so today was spent removing the window. These old sash windows were very well constructed and it took quite some time to remove them.

Photo 1
Photo 1 shows the bathroom window that needs to be blocked.

Photo 2

Photo 3

Photo 4
 Photo 4 shows a window in the garage that also required to be blocked up. The intention is that this corner will accommodate the boiler and hot water tank.
Photo 5
Photo 5 shows the bathroom window after being removed.