Day 31 - Foundation Masonry

We are already into October and the weather is deteriorating and the days are getting shorter. Getting the shell up before the winter arrives is looking less and less likely. Nevertheless, progress has been steady and the groundworks are nearing completion.

Photo 1

Photo 2
Front driveway cleared of all rubble.
Photo 3
Garage blockwork completed.

Photo 4

Photo 5
Photo 6
Photo 7
Kitchen Diner blockwork completed. Patio area ground level built up.

Photo 8
Garden looking a right mess.

We're hoping to lay the engineering bricks tomorrow if the weather stays good.