Today the concrete was poured on the main extension.
Photo 1
Photo 2
Photo 3
Sand blinded ready for DPM and then concrete. These photos show the area of the kitchen. The excavated corner was still giving us problems with the amount of water that had accumulated. It was constantly dripping from below the original foundations of the house.
Photo 4
Photo 5
With the DPM spread, down went the concrete.
Photo 6
Photo 7
Photo 8
Photo 9
Photo 9 shows the extension that will be part of the kitchen.
Photo 10
Photo 10 shows the extension that will be part of the dining area.
Photo 11
Photo 12
Photos 11 and 12 show the extension that will be part of the dining area after the concrete had dried a little.
With the BCO scheduled to visit today so that the oversite on the garage could be laid, we were hoping the weather would be kind. The excavation of the concrete pad also continued. Photo 1 Due to the rainfall over the last few days, there was a lot of water in the ground as shown in Photo 1. Photo 2 Photo 3 The water was pumped out and the area dug to a depth of 800mm below the foundations of the house. Photo 4 Photo 5 The BCO visited at 13:00 and approved the dug corner ensuring we had reached clay, and was happy for the concrete to be poured on the extension tomorrow once we had some photographs showing the layer of sand and DPM. Photo 6 Concrete was poured to form the garage floor. Photo 7 The builders also started to look at preparing for the structural steels. Photo 8 As this wall was going to be knocked through, I was concerned the picture rail was going to be damaged, so took the opportunity of using the trestles to remove ...
We've been away for two weeks, but I've now decided on a company to carry out the groundworks and take me up to DPC. I did consider hiring someone with a digger to clear the site and dig the foundations which would have saved me a good amount of money but as we've already lost a lot of time and with family commitments I decided to give the entire groundworks to someone else. This is a list of the tasks I'm expecting the contractor to have completed: Demolition of all out buildings. Demolition of utility and kitchen saving the bricks Remove all waste Dig footings 600mm wide and 1000mm deep. Remove spoil. Dig oversite down to required level and remove spoil including internal breakfast and dining rooms and hallway. - Dining room doesn’t require digging as it has a suspended floor with a 650mm void. Supply and lay concrete foundations Supply and lay concrete blocks up to DPC Supply and lay all internal drainage Supply and lay all storm and foul drainage. Re...
Comments
Post a Comment