With the BCO scheduled to visit today so that the oversite on the garage could be laid, we were hoping the weather would be kind. The excavation of the concrete pad also continued.
|
Photo 1 |
Due to the rainfall over the last few days, there was a lot of water in the ground as shown in Photo 1.
|
Photo 2 |
|
Photo 3 |
The water was pumped out and the area dug to a depth of 800mm below the foundations of the house.
|
Photo 4 |
|
Photo 5 |
The BCO visited at 13:00 and approved the dug corner ensuring we had reached clay, and was happy for the concrete to be poured on the extension tomorrow once we had some photographs showing the layer of sand and DPM.
|
Photo 6 |
Concrete was poured to form the garage floor.
|
Photo 7 |
The builders also started to look at preparing for the structural steels.
|
Photo 8 |
As this wall was going to be knocked through, I was concerned the picture rail was going to be damaged, so took the opportunity of using the trestles to remove it.