Steels arrived today.
|
Photo 1 |
The rightmost steel is the vertical post that will be positioned where the corner of the house is.
|
Photo 2 |
The drawing above shows the position of the steels with double beams used on the exterior walls. Our architect seemed to miss the requirement of 2 beams (B5 and B6), one that supports the joists above and another that supports a wall that goes up to the 2nd floor. Fortunately, the builders identified the issue before removing the walls and after confirming with the structural engineer, the correct steels were ordered.
|
Photo 4 |
|
Photo 5 |
Photos 4 and 5 show beam B2 being installed.