Day 43 - Structural Works


Photo 1
To prepare for the steel B4 to be fitted, the builders decided to remove just the inner skin of the wall first and to get the first beam in place. Once B2 is then bolted to B4, they will place the second beam in place and bolt both together.
Photo 2

Photo 3
Photos show inner skin of the wall partially removed to facilitate installing the B4 beam.

Photo 4
B2 has been fitted but needs to be secured to B4 once it goes in.