Day 98 - Brickwork
Firstly I had to arrange for another bricklayer as our initial brickie hasn't been coming for a while and now with this coronavirus pandemic, he doesn't expect to work until its passed. Having been quoted 6-8 weeks back in November, all the brickwork should have been completed months ago, and he has cost us far too much time, not to mention cost in rent alone. So we finally had to part ways.
The new bricklayer built the pier for the garage, so we're ready to install the lintel above.
The steels have also been webbed, ready for fire boarding.
Electrical cables are starting to be fitted.